Hello,
I wanted to reach back out and ask if it is possible to swap out the current ENET39 generators and demands for my own CO locations?
Furthermore, if I wanted to add generators and demands, what are the key parameters I would need to watch out for? I was made aware to NOT change or add any nodes to the system, but if I did add generators that are swapped out for ENET39 generators, can I add them and connect them to the closest node without any consequences to the transmission congestion?
Thank you,